K2018239548 (south Africa)
Eskom National Transmission Company of South Africa
What was awarded
Design, Engineering, Design Verification/Validation, Material and Equipment Procurement, Quality Management, Factory Inspection/Testing, Transport and Delivery to Site, Site Inspection, Construction, Installation, Interfacing of Control and Protection Systems (Existing and New), Testing And Commissioning, Project Management, Training, Supervision and Interface Management with other parties and all associated works and services until final completion of the work package of the 400kV,500MVar Dynamic Reactive Compensator at Aries Substation in the Northern Cape.
Award values are taken from the published eTenders award notice and shown as-is. We only display a figure where it's a single-award contract within a sane range; panel/multi-award totals are marked unconfirmed.